PRINCE2-FOUNDATION · Question #1042

PRINCE2-FOUNDATION Question #1042: Real Exam Question with Answer & Explanation

The correct answer is D. Carrying out a risk response action to respond to a particular risk. See the full explanation below for the reasoning.

Question

What is a risk actionee responsible for?

Options

  • AIdentifying risks to the project that might occur in their department
  • BOwning and authorizing the use of the risk budget to fund risk responses
  • CManaging, monitoring and controlling of all aspects of an assigned risk
  • DCarrying out a risk response action to respond to a particular risk

Community Discussion

No community discussion yet for this question.