PRINCE2-FOUNDATION · Question #1041

Which is a minimum requirement when applying the 'risk' theme?

The correct answer is D. To assess if risks might have a material impact on business justification. See the full explanation below for the reasoning.

Question

Which is a minimum requirement when applying the 'risk' theme?

Options

  • ATo identity and ring-fence an explicit risk budget within the project's budget
  • BTo describe the probability impact grid in the risk management approach
  • CTo appoint project assurance to maintain the risk register during initiation
  • DTo assess if risks might have a material impact on business justification

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    4% (2)
  • C
    11% (6)
  • D
    80% (44)