PRINCE2-FOUNDATION · Question #1041
Which is a minimum requirement when applying the 'risk' theme?
The correct answer is D. To assess if risks might have a material impact on business justification. See the full explanation below for the reasoning.
Question
Which is a minimum requirement when applying the 'risk' theme?
Options
- ATo identity and ring-fence an explicit risk budget within the project's budget
- BTo describe the probability impact grid in the risk management approach
- CTo appoint project assurance to maintain the risk register during initiation
- DTo assess if risks might have a material impact on business justification
How the community answered
(55 responses)- A5% (3)
- B4% (2)
- C11% (6)
- D80% (44)