PRINCE2-FOUNDATION · Question #1040

What should be implemented using a risk budget? 1. A request for change 2. A contingent plan 3. Actions to avoid a risk from occurring 4. Responses to dis-benefits

The correct answer is A. 1 and 2. See the full explanation below for the reasoning.

Question

What should be implemented using a risk budget? 1. A request for change 2. A contingent plan 3. Actions to avoid a risk from occurring 4. Responses to dis-benefits

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4

How the community answered

(40 responses)
  • A
    73% (29)
  • B
    15% (6)
  • C
    10% (4)
  • D
    3% (1)