The correct answer is C. A higher level of major risk will require a stage to be shorter. See the full explanation below for the reasoning.

Question

Which statement about the length of management stages in a project is CORRECT?

Options

  • AA higher level of major risk will require a stage to be longer
  • BStage length is influenced by project board availability
  • CA higher level of major risk will require a stage to be shorter
  • DUse of management stages represents a time driven control