Which statement about the length of management stages in a project is CORRECT?
The correct answer is C. A higher level of major risk will require a stage to be shorter. See the full explanation below for the reasoning.
Question
Which statement about the length of management stages in a project is CORRECT?
Options
- AA higher level of major risk will require a stage to be longer
- BStage length is influenced by project board availability
- CA higher level of major risk will require a stage to be shorter
- DUse of management stages represents a time driven control
How the community answered
(41 responses)- A5% (2)
- B10% (4)
- C71% (29)
- D15% (6)