Which activity is part of the recommended risk management procedure?

The correct answer is B. Reviewing risk management practices to ensure that they are performing effectively. See the full explanation below for the reasoning.

Question

Which activity is part of the recommended risk management procedure?

Options

  • AAllocating a budget to investigate issues
  • BReviewing risk management practices to ensure that they are performing effectively
  • CSending information to stakeholders about risks to the projects
  • DResolving conflicts between the project and the programme board

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    78% (36)
  • C
    13% (6)
  • D
    7% (3)