PeopleCert
PRINCE2-FOUNDATION · Question #1043
Which activity is part of the recommended risk management procedure?
The correct answer is B. Reviewing risk management practices to ensure that they are performing effectively. See the full explanation below for the reasoning.
Question
Which activity is part of the recommended risk management procedure?
Options
- AAllocating a budget to investigate issues
- BReviewing risk management practices to ensure that they are performing effectively
- CSending information to stakeholders about risks to the projects
- DResolving conflicts between the project and the programme board
How the community answered
(46 responses)- A2% (1)
- B78% (36)
- C13% (6)
- D7% (3)
Community Discussion
No community discussion yet for this question.