PeopleCert
PRINCE2-FOUNDATION · Question #1034
What process provides information on a team's work to the project manager?
The correct answer is D. Managing product delivery. See the full explanation below for the reasoning.
Question
What process provides information on a team's work to the project manager?
Options
- AControlling a stage
- BDirecting a project
- CManaging a stage boundary
- DManaging product delivery
How the community answered
(27 responses)- A7% (2)
- B11% (3)
- C4% (1)
- D78% (21)
Community Discussion