nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #1034

What process provides information on a team's work to the project manager?

The correct answer is D. Managing product delivery. See the full explanation below for the reasoning.

Question

What process provides information on a team's work to the project manager?

Options

  • AControlling a stage
  • BDirecting a project
  • CManaging a stage boundary
  • DManaging product delivery

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    11% (3)
  • C
    4% (1)
  • D
    78% (21)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice