PRINCE2-FOUNDATION · Question #1035

PRINCE2-FOUNDATION Question #1035: Real Exam Question with Answer & Explanation

The correct answer is C. Three. See the full explanation below for the reasoning.

Question

According to the `defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

Options

  • AOne
  • BTwo
  • CThree
  • DSix