PRINCE2-FOUNDATION · Question #1035
According to the `defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
The correct answer is C. Three. See the full explanation below for the reasoning.
Question
According to the `defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?
Options
- AOne
- BTwo
- CThree
- DSix
How the community answered
(53 responses)- A6% (3)
- B13% (7)
- C77% (41)
- D4% (2)