PRINCE2-FOUNDATION · Question #1033

PRINCE2-FOUNDATION Question #1033: Real Exam Question with Answer & Explanation

The correct answer is B. the project board. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options

  • Acorporate, programme management or the customer
  • Bthe project board
  • Cthe project manager
  • Dthe change authority

Community Discussion

No community discussion yet for this question.