The correct answer is B. the project board. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
Options
- Acorporate, programme management or the customer
- Bthe project board
- Cthe project manager
- Dthe change authority