PRINCE2-FOUNDATION · Question #1016

PRINCE2-FOUNDATION Question #1016: Real Exam Question with Answer & Explanation

The correct answer is B. Team managers may advice on tailoring to improve the management of work packages. See the full explanation below for the reasoning.

Question

How are team managers involved in tailoring PRINCE2 suit the project?

Options

  • ATeam managers are accountable for the tailoring of the work packages
  • BTeam managers may advice on tailoring to improve the management of work packages
  • CTeam managers should not be involved in tailoring PRINCE2
  • DTeam managers should document the tailoring of the work packages