PRINCE2-FOUNDATION · Question #1015
PRINCE2-FOUNDATION Question #1015: Real Exam Question with Answer & Explanation
The correct answer is A. They should be returned to corporate, programme management or customer. See the full explanation below for the reasoning.
Question
According to the `continued business justification' principle, what should happen to the funds when a project can no longer be justified?
Options
- AThey should be returned to corporate, programme management or customer
- BThey should be used to create an alternative business case for the project
- CThey should be transferred back to the project board to reassign
- DThey should be used to deliver a reduction in the scope of the project