PRINCE2-FOUNDATION · Question #1014

What is the result of the change derived from using the project's product?

The correct answer is C. Outcome. See the full explanation below for the reasoning.

Question

What is the result of the change derived from using the project's product?

Options

  • ABenefit
  • BDis-benefit
  • COutcome
  • DOutput

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    15% (6)
  • C
    73% (29)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.