Who are considered as the stakeholders in a project?

The correct answer is C. Everyone involved in or affected by the project. See the full explanation below for the reasoning.

Question

Who are considered as the stakeholders in a project?

Options

  • AOnly those benefitting the project
  • BEveryone in the corporate organization
  • CEveryone involved in or affected by the project
  • DOnly those who are users of the products

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    10% (4)
  • C
    83% (34)
  • D
    2% (1)

Community Discussion