PRINCE2-FOUNDATION · Question #1012
PRINCE2-FOUNDATION Question #1012: Real Exam Question with Answer & Explanation
The correct answer is D. To delegate day-to-day management of the project to the project manager. See the full explanation below for the reasoning.
Question
Which is a purpose of the 'directing a project' process?
Options
- ATo create and authorize the project mandate
- BTo ensure that work on products allocated to the team is authorized and agreed
- CTo control the day-to-day running of the project
- DTo delegate day-to-day management of the project to the project manager