PRINCE2-FOUNDATION · Question #1012

Which is a purpose of the 'directing a project' process?

The correct answer is D. To delegate day-to-day management of the project to the project manager. See the full explanation below for the reasoning.

Question

Which is a purpose of the 'directing a project' process?

Options

  • ATo create and authorize the project mandate
  • BTo ensure that work on products allocated to the team is authorized and agreed
  • CTo control the day-to-day running of the project
  • DTo delegate day-to-day management of the project to the project manager

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    10% (2)
  • D
    81% (17)