PRINCE2-FOUNDATION Question #1017: Real Exam Question with Answer & Explanation

The correct answer is B. the work packages provided by the project manager are agreed by the team manager. See the full explanation below for the reasoning.

Question

How does the `managing product delivery' process ensure that the team manager's perspective is provided in a work package?

Options

  • AThe work packages are defined by the team manager and supported by a team plan
  • Bthe work packages provided by the project manager are agreed by the team manager
  • CThe team plans are checked by project assurance against the work packages
  • DThe stage plan covering the work packages is created with input from the team manager