The correct answer is D. Changes to the project that do not exceed a defined budget. See the full explanation below for the reasoning.
Question
What is the change authority role permitted to authorize?
Options
- ARisks to the project
- BAdjustments to the limits on the change budget
- CChanges to stage tolerance
- DChanges to the project that do not exceed a defined budget