PRINCE2-FOUNDATION Question #1003: Real Exam Question with Answer & Explanation

The correct answer is D. Changes to the project that do not exceed a defined budget. See the full explanation below for the reasoning.

Question

What is the change authority role permitted to authorize?

Options

  • ARisks to the project
  • BAdjustments to the limits on the change budget
  • CChanges to stage tolerance
  • DChanges to the project that do not exceed a defined budget