nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #1002

PRINCE2-FOUNDATION Question #1002: Real Exam Question with Answer & Explanation

The correct answer is C. Before work to start the project commences. See the full explanation below for the reasoning.

Question

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options

  • AAfter the executive has been appointed
  • BWhen authorized by the corporate, programme management or the customer
  • CBefore work to start the project commences
  • DWhen an organization produces its business plans

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice