PRINCE2-FOUNDATION · Question #1002

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

The correct answer is C. Before work to start the project commences. See the full explanation below for the reasoning.

Question

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options

  • AAfter the executive has been appointed
  • BWhen authorized by the corporate, programme management or the customer
  • CBefore work to start the project commences
  • DWhen an organization produces its business plans

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    9% (2)
  • C
    78% (18)
  • D
    9% (2)