PRINCE2-FOUNDATION · Question #1001

PRINCE2-FOUNDATION Question #1001: Real Exam Question with Answer & Explanation

The correct answer is A. Because the people involved in a project should know what is expected of them. See the full explanation below for the reasoning.

Question

Why is it necessary to apply the 'defined roles and responsibilities' principle?

Options

  • ABecause the people involved in a project should know what is expected of them
  • BBecause the project management team should be cross-functional
  • CBecause the user and supplier interests should be involved on a need-to-know basis
  • DBecause the project manager should represent all the stakeholders of the project