The correct answer is A. Because the people involved in a project should know what is expected of them. See the full explanation below for the reasoning.
Question
Why is it necessary to apply the 'defined roles and responsibilities' principle?
Options
- ABecause the people involved in a project should know what is expected of them
- BBecause the project management team should be cross-functional
- CBecause the user and supplier interests should be involved on a need-to-know basis
- DBecause the project manager should represent all the stakeholders of the project