PRINCE2-FOUNDATION · Question #1004
PRINCE2-FOUNDATION Question #1004: Real Exam Question with Answer & Explanation
The correct answer is B. To ensure each change is managed as an exception. See the full explanation below for the reasoning.
Question
Which is a minimum requirement for applying the change theme?
Options
- ATo identify whether an issue affects the continuation of the project
- BTo ensure each change is managed as an exception
- CTo produce a breakdown of the products to be produced
- DTo tailor all changes to improve the quality of the project