PRINCE2-FOUNDATION · Question #1004

PRINCE2-FOUNDATION Question #1004: Real Exam Question with Answer & Explanation

The correct answer is B. To ensure each change is managed as an exception. See the full explanation below for the reasoning.

Question

Which is a minimum requirement for applying the change theme?

Options

  • ATo identify whether an issue affects the continuation of the project
  • BTo ensure each change is managed as an exception
  • CTo produce a breakdown of the products to be produced
  • DTo tailor all changes to improve the quality of the project