PMP · Question #982
PMP Question #982: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #982. The question stem and answer options stay visible for context.
Question
A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved. What may have caused this situation?
Options
- AThe change control plan was not followed by the project manager.
- BThe acceptance criteria were not accurately defined.
- CThe items did not appear in the project management plan.
- DThe benefits should have been managed at the organizational level.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.