PMP · Question #983
PMP Question #983: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #983. The question stem and answer options stay visible for context.
Question
Due to price inflation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced. What is the first approach the project manager should take?
Options
- AAsk the business stakeholders to reduce the number of features required for the product.
- BDelay the hiring of the additional resource until market conditions are favorable to work within
- CAsk the functional managers to source a less experienced and less expensive team member for
- DRequest the current team to analyze the work planned for the additional resource.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.