PMP · Question #972
PMP Question #972: Real Exam Question with Answer & Explanation
The correct answer is D: Monte Carlo analysis. The project team is performing a quantitative risk analysis using iterative simulations to generate a cumulative probability distribution (S-curve), which is characteristic of Monte Carlo analysis.
Question
During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome. Which method should the project manager use to assess and manage project risks?
Options
- AInfluence diagrams
- BSensitivity analysis
- CDecision tree analysis
- DMonte Carlo analysis
Explanation
The project team is performing a quantitative risk analysis using iterative simulations to generate a cumulative probability distribution (S-curve), which is characteristic of Monte Carlo analysis.
Common mistakes.
- A. Influence diagrams visually represent decisions, uncertainties, and objectives but do not involve iterating models to produce probability distributions.
- B. Sensitivity analysis determines which project risks have the most potential impact by examining the extent to which the uncertainty of each project element affects the outcome, typically displayed as a tornado diagram.
- C. Decision tree analysis is a diagrammatic technique used to evaluate possible outcomes and their probabilities when making choices under uncertainty, but it does not involve iterating a model numerous times to generate an S-curve.
Concept tested. Quantitative risk analysis; Monte Carlo simulation
Topics
Community Discussion
No community discussion yet for this question.