An organization is using a hybrid delivery approach for a complex project. In the iteration review, a subject matter expert (SME) informed the team that new legislation will be published in a few…

The correct answer is B. Discuss the change in the next sprint planning. A new legislative change impacting a hybrid project should be addressed in the next sprint planning to determine its immediate impact on current work and future iterations.

Submitted by eva_at· Apr 18, 2026Process

Question

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a subject matter expert (SME) informed the team that new legislation will be published in a few months. What should the project manager do?

Options

  • AAsk the SME to provide details after the retrospective.
  • BDiscuss the change in the next sprint planning.
  • CDiscuss the change in the next release planning.
  • DAsk the SME to provide details in the next daily standup.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    83% (25)
  • C
    10% (3)
  • D
    3% (1)

Why each option

A new legislative change impacting a hybrid project should be addressed in the next sprint planning to determine its immediate impact on current work and future iterations.

AAsk the SME to provide details after the retrospective.

Retrospective meetings are for reflecting on past performance and processes, not for introducing new external information and planning future work.

BDiscuss the change in the next sprint planning.Correct

In a hybrid or agile environment, changes are best handled at the earliest appropriate planning opportunity. Sprint planning is the ideal forum to discuss new information like upcoming legislation, allowing the team to assess its impact on the product backlog and current sprint goals, and adjust accordingly. This ensures the team can factor in potential new requirements or constraints before the next iteration begins.

CDiscuss the change in the next release planning.

Release planning covers a broader scope over multiple sprints, and while the legislation might impact releases, the immediate impact on the next iteration needs to be assessed sooner.

DAsk the SME to provide details in the next daily standup.

Daily standups are short meetings to synchronize team activities and update progress, not for detailed discussions or introducing new, significant external information that requires planning.

Concept tested: Agile change management; Sprint planning

Source: https://www.pmi.org/pmbok-guide-standards/frameworks/agile/agile-practice-guide