nerdexam
PMIPMI

PMP · Question #973

PMP Question #973: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #973. The question stem and answer options stay visible for context.

Submitted by mateo_ar· Apr 18, 2026People

Question

A key project team member had an accident and will be in the hospital for at least two months. The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them. What could the project manager have done to avoid this situation?

Options

  • AIdentified this risk and defined a risk response plan
  • BAssigned the backlog items to at least two of the team members
  • CDeveloped a knowledge transfer plan
  • DReserved a contingency budget for external consultants

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Knowledge Management#Risk Mitigation#Team Development#Cross-training
Full PMP PracticeBrowse All PMP Questions