nerdexam
PMIPMI

PMP · Question #942

PMP Question #942: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #942. The question stem and answer options stay visible for context.

Submitted by andreas_gr· Apr 18, 2026Process

Question

A project manager is leading a multiyear project. Near the end of the first year, the project manager checks to see if the whole budget allocated for the year will be used. Some features utilizing this year's budget were added later in the year as change requests, but these features will not be ready by the end of the first year. What should the project manager do?

Options

  • AAsk the team to test partially ready features and check if payment can be authorized with a
  • BAuthorize payment for the features ready this year and for the features planned for the following
  • CApproach the product owner and the financial department to create a new nonbinding contract
  • DProvide an update to the financial department regarding the status of the time line of the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Budget Management#Financial Reporting#Project Control#Stakeholder Communication
Full PMP PracticeBrowse All PMP Questions