nerdexam
PMIPMI

PMP · Question #941

PMP Question #941: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #941. The question stem and answer options stay visible for context.

Submitted by skyler.x· Apr 18, 2026Process

Question

A project in the execution phase is part of a large transformation program. The project manager for this project reports to a program manager and also heads the steering committee for this project. A steering committee meeting will be held in the following 2 weeks, during which the approach to measure the schedule performance of the project thus far will be presented. What should the project manager do in preparation for this meeting?

Options

  • APrepare to demonstrate the cost-benefit ratio, business value, and return on investment (ROI) as
  • BUpdate the cost performance index (CPI) and schedule performance index (SPI) to measure the
  • CPrepare to explain that the schedule performance index (SPI), schedule variance (SV), and other
  • DInform the program manager that the project is using an agile approach and schedule

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#Schedule Performance Index (SPI)#Schedule Variance (SV)#Performance Reporting
Full PMP PracticeBrowse All PMP Questions