nerdexam
PMI

PMP · Question #943

A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first?

The correct answer is D. Assess the impact and evaluate alternatives to accommodate the change.. When a critical project faces insufficient funding due to external changes, the project manager's first action should be to assess the impact and evaluate alternative solutions.

Submitted by chen.hong· Apr 18, 2026Process

Question

A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first?

Options

  • AReduce the scope of the project to match the available funds.
  • BPark the project until the external environment is favorable.
  • CAsk the project sponsor to look for additional funding.
  • DAssess the impact and evaluate alternatives to accommodate the change.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    6% (2)
  • D
    83% (30)

Why each option

When a critical project faces insufficient funding due to external changes, the project manager's first action should be to assess the impact and evaluate alternative solutions.

AReduce the scope of the project to match the available funds.

Reducing scope is a potential solution, but it should only be considered after a thorough impact assessment and evaluation of all available alternatives.

BPark the project until the external environment is favorable.

Parking the project is a drastic measure and a potential alternative, but it should not be the first action taken before fully understanding the impact and exploring other options.

CAsk the project sponsor to look for additional funding.

Asking for additional funding is one possible alternative, but it should be pursued only after understanding the complete impact of the shortfall and assessing other options first.

DAssess the impact and evaluate alternatives to accommodate the change.Correct

Before implementing any specific solution like reducing scope, parking the project, or seeking more funds, it is critical for the project manager to thoroughly assess the impact of the funding shortfall on project objectives and deliverables. This systematic evaluation of alternatives ensures that the most viable and strategic path forward is chosen, aligning with a structured change management process.

Concept tested: Change management and impact analysis

Source: https://learn.microsoft.com/en-us/project/manage-changes

Topics

#Change Management#Financial Constraints#Issue Management#Impact Assessment

Community Discussion

10
Brenda K.Brenda K.Jun 16, 2026

D is your quick win here. Before you touch scope, pause the work, or chase the sponsor for cash, you assess the impact and evaluate alternatives, because that analysis is what feeds every downstream decision.

29
Hiroshi T.Hiroshi T.Jun 17, 2026

Agreed on D, and the PMBOK Guide puts it under Monitor and Control Project Work where you evaluate the change impact before it ever reaches Perform Integrated Change Control for the actual disposition.

0
Hiroshi T.Hiroshi T.May 23, 2026

First leaned toward C because asking the sponsor for more money seemed like the logical escalation. But PMBOK Guide section 4.6 is clear: any change to the project, including funding constraints, requires impact assessment and evaluation of alternatives before any action is taken.

2
Fatima Z.Fatima Z.May 25, 2026

Right call on the impact assessment, and I always remember it with PIE: Propose, Impact, Evaluate before you ever touch the funding pie.

0
Carlos M.Carlos M.Jun 6, 2026

D is the right call. PMP always wants you to assess impact and evaluate options before taking action, especially when external changes hit the funding.

1
Brenda K.Brenda K.Jun 8, 2026

D is right but watch your clock on these because impact analysis sounds fast in your head and eats five minutes on the screen, so flag it, knock out two quick wins, then come back.

0
Fatima Z.Fatima Z.Jul 1, 2026

B. If the money is gone the project is parked, simple as that.

-1
Hiroshi T.Hiroshi T.Jul 3, 2026

D is correct. Per the blueprint, a parked project is explicitly defined as one that is stopped but may be resumed, whereas B conflates cancellation with parking, and the distinction matters for the exam.

0
Samuel O.Samuel O.Jul 5, 2026

Going with C here. In my experience when funding gets pulled mid-project, the PM's first move is to get the sponsor involved immediately because they control the purse strings and have the organizational clout to find money elsewhere. You can assess impact and evaluate alternatives all day long, but if the sponsor doesn't know there's a problem, none of those alternatives go anywhere. The sponsor needs to be in the loop right away so they can either hunt down additional funding or make the call on scope reductions. Everything else in D happens after that conversation, not before.

-2
Brenda K.Brenda K.Jul 6, 2026

Good reasoning on the sponsor's role, Samuel, but the exam wants D because before you pull the sponsor into a crisis you need to assess the actual impact and have alternatives ready, otherwise you are just escalating a problem without a recommendation. Think of it as a 30-second time sink, flag it, and remember the PMBOK sequence is always assess then escalate.

0
Full PMP Practice