PMIPMI
PMP · Question #943
PMP Question #943: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #943. The question stem and answer options stay visible for context.
Submitted by chen.hong· Apr 18, 2026Process
Question
A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first?
Options
- AReduce the scope of the project to match the available funds.
- BPark the project until the external environment is favorable.
- CAsk the project sponsor to look for additional funding.
- DAssess the impact and evaluate alternatives to accommodate the change.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Financial Constraints#Issue Management#Impact Assessment