nerdexam
PMIPMI

PMP · Question #937

PMP Question #937: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #937. The question stem and answer options stay visible for context.

Submitted by eva_at· Apr 18, 2026Process

Question

A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile. What should the project manager recommend?

Options

  • ANegotiate special arrangements for an agile pilot project.
  • BDefine detailed work instructions for agile project delivery.
  • CImplement and establish an agile framework for the project.
  • DHire a team of contractors for agile project delivery.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile adoption#Organizational change#Stakeholder trust#Agile frameworks
Full PMP PracticeBrowse All PMP Questions