PMIPMI
PMP · Question #936
PMP Question #936: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #936. The question stem and answer options stay visible for context.
Submitted by krish.m· Apr 18, 2026People
Question
A project manager has been working on a critical project to transform an organization's operations. The project manager had successfully completed four sprints when the innovation director was replaced. The new director placed a hold on the project until a new strategy can be put in place. What should the project manager do first?
Options
- ADiscuss the vision and possible impacts with the new director.
- BReview the risk management plan from previous projects with the new director.
- CEscalate to the project sponsor to remove the project hold.
- DSeek approval from the new director to replace the current contingency budget.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder Engagement#Communication#Issue Resolution#Change Management