nerdexam
PMI

PMP · Question #935

A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

Sign in or unlock PMP to reveal the answer and full explanation for question #935. The question stem and answer options stay visible for context.

Submitted by deeparc· Apr 18, 2026People

Question

A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

Options

  • AAdvise the team that an average of all the estimates will be used as it will be the most reliable
  • BAdvise the team that they can resolve the estimation issue and they can work on it as long as it
  • CAdvise each team member to explain the rationale for their estimate and then ask the team to
  • DAdvise the team that the project manager will determine the level of effort since the team cannot

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Estimation#Team Facilitation#Conflict Resolution#Collaborative Decision Making
Full PMP Practice