PMIPMI
PMP · Question #938
PMP Question #938: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #938. The question stem and answer options stay visible for context.
Submitted by emma.c· Apr 18, 2026Process
Question
Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule. Recently, two members submitted resignations. What should the project manager do?
Options
- AAcquire experienced additional resources from third-party suppliers.
- BAssist the team to reallocate the task to the three team members.
- CAcquire replacements by starting the hiring process immediately.
- DEscalate to the project sponsor and seek approval for a schedule delay.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Issue Management#Stakeholder Communication#Escalation#Resource Management