nerdexam
PMI

PMP · Question #911

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and

Sign in or unlock PMP to reveal the answer and full explanation for question #911. The question stem and answer options stay visible for context.

Submitted by ngozi_ng· Apr 18, 2026Process

Question

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension. What should the project manager do first?

Options

  • AAsk the team to document the impact of the risk in detail.
  • BRefer to the change log and ensure that changes are documented.
  • CRefer to the risk register and follow the mitigation plan.
  • DAsk the sponsor for their advice on the way forward.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Response#Project Execution#Change Control
Full PMP Practice