PMIPMI
PMP · Question #864
PMP Question #864: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #864. The question stem and answer options stay visible for context.
Submitted by kwame.gh· Apr 18, 2026Process
Question
During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays. What should the project manager have done to manage the issue?
Options
- AIdentified and reported the issue
- BMonitored and controlled the issue
- CIdentified the appropriate response and had it implemented
- DCommunicated any identified action to impacted stakeholders
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Issue Management#Risk Response Implementation#Corrective Action#Problem Solving