nerdexam
PMIPMI

PMP · Question #865

PMP Question #865: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #865. The question stem and answer options stay visible for context.

Submitted by rohit_dlh· Apr 18, 2026Process

Question

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project. How should the project manager report this cost?

Options

  • ACalculate the budget at completion (BAC) based on the completed and planned features.
  • BDetermine the control accounts and use a top-bottom estimate.
  • CEstimate user story points and forecast a budget for that deliverable.
  • DConsider the cost performance index (CPI) based on earned value (EV) divided by costs.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile estimation#Minimum Viable Product (MVP)#Cost estimation#User story points
Full PMP PracticeBrowse All PMP Questions