PMP · Question #829
PMP Question #829: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #829. The question stem and answer options stay visible for context.
Question
A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company. What should the project manager do first to proceed with this change?
Options
- ARequest assistance from the procurement department on the next steps.
- BEngage the services of an interpreter who understands the project domain.
- CCheck social media to determine if there are any common connections that use the new supplier.
- DBecome aware of any cultural characteristics of the new supplier that could impact negotiation.0
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.