A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components…

The correct answer is A. Request assistance from the procurement department on the next steps. When changing suppliers, especially to an international one, the project manager should first engage the procurement department. Procurement specialists manage contract cancellations, supplier vetting, and new contract negotiations, ensuring compliance and efficiency.

Submitted by noor.lb· Apr 18, 2026Process

Question

A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company. What should the project manager do first to proceed with this change?

Options

  • ARequest assistance from the procurement department on the next steps.
  • BEngage the services of an interpreter who understands the project domain.
  • CCheck social media to determine if there are any common connections that use the new supplier.
  • DBecome aware of any cultural characteristics of the new supplier that could impact negotiation.0

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    4% (1)
  • C
    13% (3)
  • D
    8% (2)

Why each option

When changing suppliers, especially to an international one, the project manager should first engage the procurement department. Procurement specialists manage contract cancellations, supplier vetting, and new contract negotiations, ensuring compliance and efficiency.

ARequest assistance from the procurement department on the next steps.Correct

Requesting assistance from the procurement department on the next steps is the most appropriate first action because procurement specialists are experts in vendor management, contract termination, international sourcing, and negotiating new contracts. They possess the necessary legal knowledge, established processes, and relationships to facilitate a smooth transition to a new overseas supplier, ensuring compliance and optimal terms.

BEngage the services of an interpreter who understands the project domain.

Engaging an interpreter, while potentially useful later, is premature; the initial step involves internal processes and strategic procurement guidance before specific communications are needed.

CCheck social media to determine if there are any common connections that use the new supplier.

Checking social media for common connections is a passive and informal approach that is not a formal first step for a critical procurement change and does not leverage internal expertise.

DBecome aware of any cultural characteristics of the new supplier that could impact negotiation.0

While cultural awareness is important for international negotiations, it is a secondary consideration. The *first* step is to involve the internal department responsible for managing supplier relationships and contracts.

Concept tested: Procurement process and vendor change management

Topics

#Procurement Management#Supplier Management#Contract Termination#Organizational Process

Community Discussion

5
Bao N.Bao N.Jul 5, 2026

A is the right call here. The contract is being canceled and a new supplier is coming in, so the procurement department owns the transition steps and the PM should loop them in before doing anything else. B and D both jump the gun because you handle language and cultural considerations during planning and negotiating, not before you even know what the procurement process requires. C is just a distractor that sounds vaguely useful but has nothing to do with proper vendor change management. Saw this one on a practice set last week and the key is catching that word "first" in the stem.

11
Ingrid P.Ingrid P.Jul 1, 2026

A. Procurement owns contract changes, you do not source your own next steps.

2
Carlos M.Carlos M.Jul 2, 2026

Agreed, and the trap is people see change request and immediately think project manager when the vendor contract side is strictly procurement.

0
Carlos M.Carlos M.Jul 5, 2026

A is right. Procurement owns the contract switch, get them involved first.

2
Bao N.Bao N.Jul 8, 2026

A is right but flagging it as a vendor change request in your tracking system before procurement picks up the phone keeps the audit trail clean.