A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project. What action should the project manager take?
Options
- AConsult with team members and allow them to make a decision.
- BAccommodate the change request to serve the client's needs.
- CConvince the client not to make changes to the project.
- DMake transactional decisions focusing on the project goals.8
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Stakeholder Management#Value Delivery#Client Satisfaction