PMP · Question #830

A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project. What action should the project manager take?

The correct answer is B. Accommodate the change request to serve the client's needs. When a client requests a design change that could add value, the project manager should accommodate the change request by initiating the formal change control process. This ensures the change is properly evaluated, planned, and implemented to meet client needs while managing…

Submitted by mateo_ar· Apr 18, 2026People

Question

A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project. What action should the project manager take?

Options

  • AConsult with team members and allow them to make a decision.
  • BAccommodate the change request to serve the client's needs.
  • CConvince the client not to make changes to the project.
  • DMake transactional decisions focusing on the project goals.8

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    79% (26)
  • C
    12% (4)
  • D
    6% (2)

Why each option

When a client requests a design change that could add value, the project manager should accommodate the change request by initiating the formal change control process. This ensures the change is properly evaluated, planned, and implemented to meet client needs while managing project scope.

AConsult with team members and allow them to make a decision.

While consulting with team members is necessary for evaluation, allowing *them* to make the ultimate decision bypasses the project manager's responsibility for change control and client relationship management.

BAccommodate the change request to serve the client's needs.Correct

Accommodating the change request to serve the client's needs is the appropriate response, provided it follows a formal change control process. While a project manager must manage scope, a client-requested change that *adds value* should be welcomed, evaluated, and integrated if feasible. The project manager's role is to ensure client satisfaction and project success, which often involves adapting to evolving requirements through a structured change management approach.

CConvince the client not to make changes to the project.

Convincing the client not to make changes, especially if they add value, is counterproductive to client satisfaction and potentially limits the project's ultimate success and utility.

DMake transactional decisions focusing on the project goals.8

Making "transactional decisions focusing on project goals" can be too rigid; project goals evolve, and a project manager must balance adherence to the plan with flexibility to deliver maximum value, especially when the client identifies an enhancement.

Concept tested: Change management and client value

Topics

#Change Management#Stakeholder Management#Value Delivery#Client Satisfaction

Community Discussion

No community discussion yet for this question.