nerdexam
PMIPMI

PMP · Question #828

PMP Question #828: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #828. The question stem and answer options stay visible for context.

Submitted by yaw92· Apr 18, 2026Process

Question

A new government regulation has mandated that all team members will need to work remotely for the duration of the next iteration. This means backlog priority changes will need to be completed What should the project manager do?

Options

  • ACommunicate the new regulation to the project sponsor during the next retrospective.
  • BInform the product owner of the required change as soon as possible.
  • CReprioritize the backlog and share it with the team as soon as possible.
  • DAsk the team facilitator to reprioritize the backlog based on the new regulation.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile roles#Product Owner responsibilities#Backlog management#External change impact
Full PMP PracticeBrowse All PMP Questions