A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned. What should the project manager do next?
Options
- ARequest the project sponsor to fund this change as it is a new regulation, then order the materials
- BAssess the impact of the required change and consult with the executive sponsors to determine
- CAsk the designers to start designing a solution for this new requirement while the project is
- DHave the company's lawyers write to the municipality and reject the change as it was not part of
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#External Regulations#Change Management#Impact Assessment#Stakeholder Engagement