nerdexam
PMI

PMP · Question #732

A project manager is defining the sprint goals with the team. A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team m

The correct answer is A. Request to meet with the team member and ask that any issues be escalated separately.. When a team member is openly criticizing sprint goals and causing disagreement during a meeting, the project manager should request to meet with the team member separately to address their concerns. This allows the meeting to progress while ensuring the team member's issues are r

Submitted by hans_de· Apr 18, 2026People

Question

A project manager is defining the sprint goals with the team. A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members. How should the project manager handle this situation?

Options

  • ARequest to meet with the team member and ask that any issues be escalated separately.
  • BReprimand the team member and provide immediate coaching on goal alignment.
  • CProceed with defining the goals with the team members given the majority approval from the
  • DApproach the team member with empathy and obtain agreement through collaboration.

How the community answered

(45 responses)
  • A
    80% (36)
  • B
    2% (1)
  • C
    13% (6)
  • D
    4% (2)

Why each option

When a team member is openly criticizing sprint goals and causing disagreement during a meeting, the project manager should request to meet with the team member separately to address their concerns. This allows the meeting to progress while ensuring the team member's issues are respectfully acknowledged and managed.

ARequest to meet with the team member and ask that any issues be escalated separately.Correct

During a group meeting like sprint goal definition, maintaining focus and allowing the team to progress is crucial. By requesting to meet with the team member separately, the project manager acknowledges their concerns without derailing the main meeting, demonstrating respect while ensuring the team can continue to define the goals, and addressing underlying issues privately.

BReprimand the team member and provide immediate coaching on goal alignment.

Reprimanding a team member in a public setting can be counterproductive, damaging morale and trust, and may not effectively resolve the underlying issue.

CProceed with defining the goals with the team members given the majority approval from the

Proceeding without adequately addressing the dissenting team member's concerns, especially one responsible for acceptance testing, can lead to disengagement and potentially unaddressed risks or quality issues.

DApproach the team member with empathy and obtain agreement through collaboration.

While empathy and collaboration are important, trying to obtain agreement through extensive collaboration during the main meeting when one person is actively criticizing can consume excessive time and prevent the team from achieving its primary objective of defining the sprint goals.

Concept tested: Conflict resolution and meeting facilitation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/resource-management

Topics

#Conflict Resolution#Team Management#Agile Practices#Facilitation

Community Discussion

No community discussion yet for this question.

Full PMP Practice