PMIPMI
PMP · Question #716
PMP Question #716: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #716. The question stem and answer options stay visible for context.
Submitted by lucia.co· Apr 18, 2026Process
Question
A project manager is managing a construction project that is facing challenges. There is schedule overrun, cost overrun, and the client is unhappy with the specific scope progress. What should the project manager do first?
Options
- AReview the scope and project objectives.
- BEnforce the penalty clause on the supplier.
- CTake action to reduce the cost overrun.
- DWork with the client on the scope completion.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Scope Management#Issue Resolution#Stakeholder Engagement#Project Baselines