nerdexam
PMIPMI

PMP · Question #717

PMP Question #717: Real Exam Question with Answer & Explanation

The correct answer is A: Perform an analysis to assess the Impact on the project.. When new financial regulations cause a major project scope change, the project manager should first perform an analysis to assess the impact on the project.

Submitted by emma.c· Apr 18, 2026Process

Question

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope. How should the project manager respond to this requirement?

Options

  • APerform an analysis to assess the Impact on the project.
  • BProceed with the existing company governance policy.
  • CEscalate the issue to upper management and let them decide.
  • DDirectly comply with the financial regulations.

Explanation

When new financial regulations cause a major project scope change, the project manager should first perform an analysis to assess the impact on the project.

Common mistakes.

  • B. Proceeding with the existing governance policy when new financial regulations are in place would lead to non-compliance, exposing the company to significant legal and financial risks.
  • C. Escalating the issue to upper management is often a necessary step for major changes, but it should typically follow the project manager's initial assessment of the impact, allowing them to present data-backed options or recommendations.
  • D. Directly complying with new regulations without a prior impact analysis could lead to unforeseen problems, inefficient implementation, or conflicts with existing project constraints and objectives.

Concept tested. Change Management, Regulatory Compliance

Reference. https://www.pmi.org/learning/library/change-management-project-management-8698

Topics

#Change Management#Scope Change#Impact Analysis#Regulatory Compliance

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions