A project manager holds periodic progress review meetings to discuss issues. What should the project manager do first on the agenda?

Options

  • AElaborate the risk mitigation strategy and risk register.
  • BUpdate resolution approaches and action assignments.
  • CFormulate project management plan integration.
  • DProduce lessons learned documentation.