nerdexam
PMIPMI

PMP · Question #607

PMP Question #607: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #607. The question stem and answer options stay visible for context.

Submitted by marco_it· Apr 18, 2026Business Environment

Question

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach. What should the project manager do?

Options

  • AReview the communications management plan to identify new stakeholders.
  • BDefine a risk management plan for the new approach, as needed.
  • CDefine a project management plan for the new approach, as needed.
  • DReview the benefits realization plan to include the cost of the change.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Benefits Realization#Organizational Change#Change Impact Analysis#Value Management
Full PMP PracticeBrowse All PMP Questions