A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with…

The correct answer is C. Ask the team to fast-track the project and perform tasks that do not require calculations. When a software license expires and blocks project tasks, the project manager should first direct the team to work on other non-dependent tasks to maintain productivity. Simultaneously, the project manager should initiate efforts to resolve the license issue.

Submitted by ricky.ec· Apr 18, 2026Process

Question

A project team member just informed the project manager that the license for the software that the team uses to perform calculations has just expired. As a result, the team cannot continue with their project tasks. What should the project manager do first?

Options

  • AIssue a formal complaint to the project sponsor claiming a lack of proper tools.
  • BAsk the team members to find an alternative way to perform calculations.
  • CAsk the team to fast-track the project and perform tasks that do not require calculations.
  • DMeet with the IT team to evaluate how fast the software license can be renewed.

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    15% (5)
  • C
    76% (26)
  • D
    6% (2)

Why each option

When a software license expires and blocks project tasks, the project manager should first direct the team to work on other non-dependent tasks to maintain productivity. Simultaneously, the project manager should initiate efforts to resolve the license issue.

AIssue a formal complaint to the project sponsor claiming a lack of proper tools.

Issuing a formal complaint to the project sponsor is not a productive first step; it focuses on blame rather than immediate problem-solving and action to mitigate project delays.

BAsk the team members to find an alternative way to perform calculations.

Asking the team to find an alternative way to perform calculations without first assessing the license renewal speed or alternative tasks is not the most efficient initial step, as finding an alternative might be time-consuming and temporary.

CAsk the team to fast-track the project and perform tasks that do not require calculations.Correct

In an agile or adaptive environment, when a significant impediment blocks specific tasks, the project manager's primary immediate action is to ensure the team remains productive. By shifting focus to tasks that do not require the affected software, the project manager minimizes downtime and continues delivering value while the root cause (license renewal) is being addressed in parallel.

DMeet with the IT team to evaluate how fast the software license can be renewed.

While meeting with the IT team is a crucial step to resolve the license issue, it is not the *first* action to mitigate the immediate impact on project progress; the team should continue with other work in parallel to avoid complete stagnation.

Concept tested: Agile impediment handling and team productivity

Source: https://www.pmi.org/-/media/pmi/documents/public/pdf/agile/agile-practice-guide.pdf

Topics

#Issue Management#Problem Solving#Team Productivity#Resource Management