nerdexam
PMI

PMP · Question #553

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers les

Sign in or unlock PMP to reveal the answer and full explanation for question #553. The question stem and answer options stay visible for context.

Submitted by neha2k· Apr 18, 2026Process

Question

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project. What should the project lead do?

Options

  • AAsk that estimations be provided only by senior developers.
  • BRecommend a different estimation method in the retrospective.
  • CAllocate more time for estimation in the sprint planning.
  • DReview and update the estimations in the daily standup.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile estimation#Sprint retrospective#Team velocity#Process improvement
Full PMP Practice