PMP · Question #553
PMP Question #553: Real Exam Question with Answer & Explanation
The correct answer is B: Recommend a different estimation method in the retrospective.. For a new agile team struggling with high velocity variation and under-delivery, a new project lead should recommend exploring different estimation methods in the retrospective.
Question
An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project. What should the project lead do?
Options
- AAsk that estimations be provided only by senior developers.
- BRecommend a different estimation method in the retrospective.
- CAllocate more time for estimation in the sprint planning.
- DReview and update the estimations in the daily standup.
Explanation
For a new agile team struggling with high velocity variation and under-delivery, a new project lead should recommend exploring different estimation methods in the retrospective.
Common mistakes.
- A. Limiting estimations to only senior developers undermines the principle of whole-team ownership and self-organization in agile, potentially leading to less accurate estimates due to a lack of diverse perspectives.
- C. Allocating more time for estimation doesn't guarantee improved accuracy if the underlying method is flawed or the team isn't skilled in its application; the focus should be on method effectiveness.
- D. Reviewing and updating estimations during a daily standup is too disruptive; the daily standup is for quick progress updates and impediment identification, not detailed re-estimation of sprint backlog items.
Concept tested. Agile estimation and continuous improvement
Reference. https://www.scrum.org/resources/what-is-a-sprint-retrospective
Topics
Community Discussion
No community discussion yet for this question.