PMIPMI
PMP · Question #535
PMP Question #535: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #535. The question stem and answer options stay visible for context.
Submitted by joshua94· Apr 18, 2026Process
Question
A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only. What should the project manager do?
Options
- AAsk the sponsor to increase the budget and schedule of the project to accommodate the
- BAssess the impact to the scope and submit a change request for approval of the two locations
- CDiscuss with the sponsor that the project scope is approved and it is not possible to include two
- DEncourage the sponsor to start another project for the additional location so that the current
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Scope Management#Change Control#Project Charter#Stakeholder Engagement