nerdexam
PMIPMI

PMP · Question #534

PMP Question #534: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #534. The question stem and answer options stay visible for context.

Submitted by yasin.bd· Apr 18, 2026Process

Question

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application. Which estimation technique should the project manager recommend?

Options

  • AAnalogous estimating
  • BParametric estimating
  • CPlanning poker
  • DThree-point estimating

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Estimation techniques#Three-point estimating#Schedule management#Uncertainty management
Full PMP PracticeBrowse All PMP Questions