A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly. What should the project manager do next?

The correct answer is B. Invite the stakeholders to discuss a mitigation plan.. An unexpected team member departure in the late stages of a project is a significant issue requiring stakeholder involvement to formulate a viable mitigation plan.

Submitted by valeria.br· Apr 18, 2026People

Question

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly. What should the project manager do next?

Options

  • ATake on some of the necessary work to minimize the impact.
  • BInvite the stakeholders to discuss a mitigation plan.
  • CDetail the reason for the project delay in the status report.
  • DRegister an issue and escalate it to the project sponsor.

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    81% (38)
  • C
    4% (2)
  • D
    4% (2)

Why each option

An unexpected team member departure in the late stages of a project is a significant issue requiring stakeholder involvement to formulate a viable mitigation plan.

ATake on some of the necessary work to minimize the impact.

A project manager taking on development work directly is generally discouraged as it deviates from their primary management role and could lead to burnout or neglect of other project responsibilities.

BInvite the stakeholders to discuss a mitigation plan.Correct

A sudden team member departure during a critical phase like the fifth iteration out of six constitutes a major risk or issue that could severely impact project delivery. Involving stakeholders is crucial because they represent key interests and can help decide on the best mitigation strategy, such as reassigning tasks, adjusting scope, or extending the timeline, ensuring collective agreement and support for the chosen path.

CDetail the reason for the project delay in the status report.

Simply detailing the reason for a delay in a status report is reactive and does not proactively address the problem or develop a solution.

DRegister an issue and escalate it to the project sponsor.

While registering an issue is correct, escalating directly to the project sponsor without first formulating a proposed mitigation plan or discussing with relevant stakeholders might be premature and less effective.

Concept tested: Issue management and stakeholder engagement in project crisis

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/manage-stakeholder-engagement

Topics

#Stakeholder Engagement#Issue Management#Resource Management#Mitigation Planning