Question
The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources. What strategy should the project manager use in order to keep delivering value in a restricted environment?
Options
- AReduce the project staff and adjust the scope and timelines accordingly in support of the budget
- BBalance the project team in order to accommodate the budget challenges, and provide training to
- CPrioritize the product backlog looking for high business value and low effort, and adjust the project
- DRestrict the project scope only to basic critical features and run the project with the current
Unlock PMP to see the answer