PMIPMI
PMP · Question #461
PMP Question #461: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #461. The question stem and answer options stay visible for context.
Submitted by luis.pe· Apr 18, 2026Process
Question
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals. What two options will help the team initially address this obstacle? (Choose two.)
Options
- AEscalate the issue to the project sponsor
- BReview and update dependencies
- CSchedule a retrospective
- DConduct a root cause analysis
- ECreate a risk management plan
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Problem-solving#Root Cause Analysis#Dependency Management#Issue Management