nerdexam
PMIPMI

PMP · Question #46

PMP Question #46: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #46. The question stem and answer options stay visible for context.

Submitted by lukas.cz· Apr 18, 2026Process

Question

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones. When will the project manager be able to provide the requested information?

Options

  • ADuring the planning phase, when processes for scope definition and activity duration and
  • BClose to the end of the project, as the forecasts will be more accurate and most risks will already
  • CIn the initiation process, as it happens concurrently with the project contract and project charter
  • DAs soon as possible, as project delays can be significantly avoided when a schedule is developed

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Project Planning#Milestone Definition#Project Lifecycle#Process Groups
Full PMP PracticeBrowse All PMP Questions